Georgiou Completes Australian Earthworks Project Two Months Ahead Schedule

Georgiou Completes Australian Earthworks Project Two Months Ahead Schedule

Georgiou image

VisionLink Haul Monitoring in parallel with LOADRITE X2350 excavator scales to provide better visibility to optimize haul routes and truck payload.

Overview

Georgiou Group is a national building construction, engineering and property development company, delivering major projects across Western Australia, Queensland, Victoria and New South Wales. They are a low-cost, high performance company and wanted to improve productivity and cost control on a recently-awarded land development project awarded.  This six-month project in Alkimos, approximately 50 kilometers north of Perth, in Western Australia, involved moving 600,000 cubic meters of sand, rock and limestone 1.5 kilometers between the cut and fill zones. The site measured 2 kilometers long by approximately 600 meters wide. Georgiou turned to SITECH Western Australia (SITECH WA) and Trimble for help understanding payloads, movement of material, and the productivity of operators and mass haul routes.

Previous method

In the past, Georgiou manually collected payload data to map to cost centres. They had no access to real-time data on productivity and material movement leading to potentially inaccurate and sometimes delayed information.

Innovation

On this project, the team adopted a range of Trimble® solutions including: the 3D GCS900 Grade Control System, 2D Project Monitoring on Haul assets and LOADRITE X2350 excavator scales. Data from this hardware was used by InsightHQ and VisionLink® software to improve productivity, increase data transparency and accuracy, and therefore reduce costs. Georgiou used Business Center – Heavy Construction Edition (HCE) software for Mass Haul Analysis and Design Creation. Utilization of SCS900 Site Controller software and Unmanned Aerial Vehicles augmented the site solution.

Benefits:

  • 33% project time reduction and 25% hauling productivity gain through transparency of payloads
  • Real-time visibility of cost to move material, load times, and other vital production data
  • Quickly-defined optimal haul zones using Business Center – HCE
  • Ability to monitor where material was removed and dropped
  • Improved productivity with access to accurate, automatic production and volume reports

Solution Detail

Georgiou Project Manager Jim Ryan and Georgiou Machine Control Lead Ian Hitsert led the project and began by equipping two 125-tonne excavators and one 85-tonne excavator with the LOADRITE X2350 excavator scales and 2D VisionLink monitoring devices. The LOADRITE X2350 excavator scales reported live data to InsightHQ for analysis and goal-setting. Monitoring devices were also fitted to 16 dump trucks. The primary goals focused on productivity, tracking material moved, reducing their carbon footprint and keeping staff a safe distance from machines on the jobsite. Trimble’s VisionLink – a fleet, asset and site productivity management software – was then used to capture data from dump trucks to be analyzed and displayed through dashboards available on iPad. The LOADRITE system gave excavator operators precise weight information to optimally load dump trucks. Trimble GCS900 GPS systems were used to track project progress and monitor material movement and the locations where material was cut and filled. Business Center – HCE created a digital terrain model of the Alkimos project site. They also used Business Center – HCE’s Corridor Mass Haul module to define haul zones and perform a comprehensive mass haul analysis of the project.

Conclusion

“The technology solution provided by Trimble and the working partnership developed with SITECH WA has allowed Georgiou to discover the benefits this technology can deliver to the business for earthworks projects of this size and nature. The positive outcomes from this project have enabled Georgiou to utilise this technology to manage productivity on future projects. With a better understanding of the Trimble hardware and software, we are now challenging Trimble to provide additional functionality to further improve productivity,” said Hitsert.

Cost savings Ryan estimates the cost savings to the project was in the order of 20% explaining one of the biggest advantages of the system was being able to determine and track the cost of moving a cubic meter of dirt on a daily basis. Project management could see how quickly trucks were being loaded and show operators their individual productivity data compared to other operators.

“We had two guys running two PC 1250 120 tonne excavators and noticed production on one machine was slower than the other,” said Ryan. “We swapped these guys around to see if it was the truck; and it wasn’t. With accurate data about payloads, we could see this kind of information immediately and easily start the conversation as we had actual data to point to. We found ways to improve their performance with more accountability through daily, even hourly, production check-ins.”

Automation of accurate, real-time data

Operators running excavators and dump trucks were able to work as normal, loading material from the first cut zone and dropping it at the fill zone. The Trimble SNM940 Connected Site Gateway relayed production data to VisionLink and InsightHQ to gather payload information. Ryan explains that data from the LOADRITE scales centralized performance and productivity information across the range of machine sizes, brands and models.

Ryan and the equipment operators had real-time information about load counts, idle times, time stamps when trucks are loaded, and travel time for material movement. From the office and using iPads in the field, supervisors were able to access information immediately and work with operators to improve productivity. Ryan explains that on a daily basis supervisors could graphically see project status, comparing a six-month project timeline to productivity to date.

This replaced our old method of manually capturing data which could sometimes be inaccurate and days behind.

“Today, with Trimble Business Center – HCE and VisionLink, we have the real time cost and production status at the touch of a button,” said Ryan. “We don’t have to go out and do any manual spreadsheets, collecting load counts for all machines and mapping them to cost centers. The technology doesn’t build the job for you, but we’ve taken full advantage of using the data to work more efficiently and it has had a positive impact on the bottom line.”

To track the progress of material moved at the end of each month, the Georgiou team also ran Trimble’s UAV system to capture point cloud data and build a terrain model of the Alkimos site.

“Because earth was being hauled continuously, there was lag time from when we captured data from the UAV system to when we processed it and created reports,” said Hitsert. “In Business Center – HCE we would re-compute our corridor mass haul volumes to design and track progress in terms of overall volume. Essentially, we would re-compute Mass Haul, load it into Visionlink and back date it to the day of the UAV flight – which was a big plus for us because then we had a full picture in VisionLink of how much material was moved from that date forward.”

Within two weeks of using both LOADRITE excavator scales and InsightHQ reports, Ryan and the team realized that although each truck was full by volume, they were under-loaded by weight due to lower density material and could take a further 8-tonnes each.

“We saw quickly from our haul routes and material production reports that loading each truck with 32-tonnes of material was inefficient,” said Hitsert. “To improve material moved per day, Georgiou’s internal Plant Department fitted steel plates around the tops of all dump trucks so we could carry 40 tonnes of rock, sand and limestone instead of 32. We never would have known this without the Trimble technology.